18.4. If the contractor fails to submit explanations within the time set in section 18.3 or if, despite the explanations provided, the public body still considers the price to seem unusually low, the public body forwards the tender to a committee set up for that purpose for analysis.
The committee is composed of the contract rules compliance monitor in the public body and at least 3 members designated by the chief executive officer of the public body who are not involved in the awarding process.
The contract rules compliance monitor supervises the committee’s work.
O.C. 431-2013, s. 5.